Kyle CIP projects underway

By Megan Wehring

Several projects are well underway in Kyle with plans for some to be completed by the end of August.

Lehman Road, near Lehman High School, construction is 91% complete along with the paving finished. It’s currently closed from Hallie Dr to Bunton Creek Rd. The road is expected to be completed by the end of the month.

Based on pay estimates, the Burleson Road project is currently 83% complete. Paving is complete except for Rodriguez to the roundabout. Traffic signals and lights are in progress. Substantial completion is planned for this month.

The SouthSide Wastewater Improvements Project is 59% complete. One crew is working on the Post Road lift station. The other crews are working on water lines near Public Works and bore at Post Road near I-35.

The Wastewater Treatment Plant expansion is at 5.21% completion. More project information will be posted near trails for residents.

Comment on this Article

About Author

Megan Navarro (Wehring) graduated from Texas State University in May 2020 with a bachelor's degree in journalism and mass communication. In June 2020, she started a summer internship at the Hays Free Press/News-Dispatch through the Dow Jones News Fund and Texas Press Association. She then earned her way to a reporter position later that summer and now, she serves as the editor of the newspaper. Working for a small publication, Navarro wears multiple hats. She has various responsibilities including managing a team of reporters, making editorial decisions, overseeing social media posts, fact checking, writing her own articles and more. Navarro has a heart for storytelling and she believes that journalists are equipped to share the stories that are important to the community.