DACY LN. WIDENING PROJECT: Dacy Lane: Construction Update – Week Ending 06/12/2021

Construction activities performed during the period of 6/6/2021 – 6/12/2021 are listed below:[pdf-

  • Earthwork Operations: Austin Wood
    • Cleared ROW and hauled brush off site between Sta 116 and 125 LT & RT

Cleared ROW between Sta 82 and 92 LT & RT (98% complete)

  • Earthwork Operations: Jordan Foster
    •   Continued excavation between Sta 126 and 146 and hauling over burden off site
  • Utility Operations: Jordan Foster
    • Waterline installation continued between Sta 153 and 99. Complete to Sta 100 (35% total)
    • RCP Crew didn’t work on project this week

Anticipated activities for the next week are as follows:

  • Earthwork Operations: Austin Wood
    • Continue hauling brush from clearing operation of site between STA 82 and 92 (LT & RT)
  • Earthwork Operations: Jordan Foster

Continue working subgrade between Sta 126 and 146. Start Lime treatment for same Sta range

  • Utility Operations: Jordan Foster
    • Start RCP installation at Chapa School Driveway (Fri-Sat)
    • Start Culvert A